成本管理外文文献翻译
外文文献及翻译
Project Budget Monitor and Control
Author:Yin Guo-li
Nationality:American
Derivation: Management Science and Engineering. Montreal: Mar 20, 2010 .
With the marketing competitiveness growing, it is more and more critical in budget control of each project. This paper discusses that in the construction phase, how can a project manager be successful in budget control. There are many methods discussed in this paper, it reveals that to be successful, the project manager must concern all this methods.
1. INTRODUCTION
The survey shows that most projects encounter cost over-runs (Williams Ackermann, Eden, 2002,pl92). According to Wright (1997)'s research, a good rule of thumb is to add a minimum of 50% to the first estimate of the budget (Gardiner and Stewart, 1998, p251). It indicates that project is very complex and full of challenge. Many unexpected issues will lead the project cost over-runs. Therefore, many technologies and methods are developed for successful monitoring and control to lead the project to success. In this article, we will discuss in the construction phase, how can a project manager to be successful budget control.
2. THE CONCEPT AND THE PURPOSE OF PROJECT CONTROL AND MONITOR
Erel and Raz (2000) state that the project control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliver the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it. The purpose of monitor and control is to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target。
3. SETTING UP AN EFFICIENT CONTROL SYSTEM
For the purpose of achieving cost target, the manager need to set up an efficient management framework including: reporting structure, assessing progress, and communication system. The employees' responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).
4. COST MONITOR AND CONTROL
4.1 Ranking the priority of monitoring
In construction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determined by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Secondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are committed elsewhere. Thirdly, monitoring the activities with less than a specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).
4.2Methods of cost control
The main cost of a project includes staff cost, material cost and delay cost. To control these cost, managers should first set up a cost control system to: a) Allocate responsibilities for administration and analysis of financial data
b) Ensure all costs are properly allocated against project codes
c) Ensure all costs are genuinely in pursuit of project activities
d) Check that other projects are not using the budget.
Then, managers should monitor and control change to the project budget. It means the following things:
a) Concerned with key factors that cause changes to the budget
b) Controlling actual cost changes as they occur
- Monitor cost performance to detect variances
- Record all appropriate changes accurately in the cost baseline
- Preventing incorrect, unauthorized changes being included in the cost baseline
- Determine positive and negative variances
- Integrated with all other control processes (scope, change, schedule, quality)
As a project is dynamic, sometimes the project managers know the project is going out off target by monitoring, but don't know the best action to take. In this circumstance, net present value (NPV) should be used as an ongoing monitor and control mechanism, because NPV takes account of the time element and discounts future cash flows, it is the result of the time effect on cash
4.3 Change monitor and control
Voropajev (1998) states that dynamic changes of project environment will influence the process of project implementation, the project itself and may cause heightened risk. When carried out some activities, the methods different from that in the original plan must be used to keep the proc …… 此处隐藏:5546字,全部文档内容请下载后查看。喜欢就下载吧 ……
相关推荐:
- [教育文库]夜场KTV服务员的岗位职责及工作流程[1]
- [教育文库]企划、网络、市场绩效考核方案
- [教育文库]学党史、知党情、强党性--“党的基本理
- [教育文库]2016年高考物理大一轮总复习(江苏专版
- [教育文库]干部廉洁自律自查自纠的报告
- [教育文库]2010年北京大学心理学系拟录取硕士研究
- [教育文库]资金时间价值练习题及答案
- [教育文库]保护环境的心得体会
- [教育文库]英语角内容:英语趣味小知识
- [教育文库]档案收集与管理工作通知
- [教育文库]劳动规章制度范本范本
- [教育文库]高考物理一轮复习课后限时作业1运动的
- [教育文库]机械工艺夹具毕业设计195推动架设计说
- [教育文库]通用技术教学比赛说课稿2
- [教育文库]2018年四年级英语下册 Module 7 Unit 2
- [教育文库]第2章 宽带IP网络的体系结构
- [教育文库]九年级化学第五单元课题3《根据化学方
- [教育文库]小学英语六年级情态动词用法归纳
- [教育文库]甲级单位编制窑井盖项目可行性报告(立
- [教育文库]2016-2021年中国城市规划行业全景调研
- 高考英语听力十大场景词汇总结
- 全省领导班子思想政治建设座谈会会议精
- 人教版新课标高一英语提优竞赛试题 下
- 江西省2014年生物中考试题
- 长沙镇食品药品安全事故应急预案
- 《金刚石、石墨和C60》片段教学设计
- 福州教育学院(王旭东)
- 基于EDA音乐播放器的设计
- 9、古诗两首《夜书所见》《九月九日忆
- 小学语文课外阅读有效策略探讨
- 贵州文化产业发展成支柱产业的问卷调查
- 膀胱类癌的诊治体会(附3例报告)
- 发动机积碳产生的原因
- Configuring Code Composer Studio for
- 学生良好的心理素质如何培养点滴谈
- 46 电沉积法制备锂离子电池用硅-锂薄膜
- 美舍雅阁公司管理中各部门职责
- 去壳剥皮的小妙招
- 六自由度运动平台的仿真研究
- Pride and Prejudice(傲慢与偏见)