EU GMP指南附件15:确认和验证
EU GMP 指南附件 15:确认和验证(中英文)EU GMP 指南附件 15:确认和验证(中英文)
EUROPEAN COMMISSIONENTERPRISE DIRECTORATE-GENERAL Single market, regulatory environment, industries under vertical legislation Pharmaceuticals and cosmetics
Brussels, July 2001
Working Party on Control of Medicines and Inspections Final Version of Annex 15 to the EU Guide to Good Manufacturing Practice 欧盟 GMP 附件 15 终稿 Title: Qualification and validation 题目:确认和验证First discussion in drafting group 起草组的初步讨论 Discussion at the working Party on Control of Medicines and Inspection for release for consultation 药物控制和检查工作组讨论 Pharmaceutical Committee 药物委员会 Released for consultation 讨论稿完成 Deadline for comments 征求意见结束 Final approval by Inspector’s working party 检查官工作组最终批准 Pharmaceutical Committee (for information) 药物委员会(供参考) Date for coming into operation 实施日期 16 September 1999
28 September 1999 30 October 1999 28 February 2000 December 2000 April 2001 September 2001
Note that this document is based in the PICS/S recommendations
注意本文件基于PICS/S建议。
Table of Contents 目录
Page页
1. Qualification and Validation 确认和验证 3
2. Planning for Validation 验证计划 4
3. Documentation 文件 4
4. Qualification 确认 5
5. Processs Validation. 工艺验证 6
6. Cleaning Validation 清洁验证 7
7. Change Control 变更控制 8
8. Revalidation 再验证 9
9. Glossary 术语 10
QUALIFICATION AND VALIDATION 确认和验证
Principle 原则
1. This Annex describes the principles of qualification and validation which are applicable to the manufacture of medicinal products. It is a requirement of GMP that manufacturers identify what validation work is needed to prove control of the critical aspects of their particular operations. Significant changes to the facilities, the equipment and the processes, which may affect the quality of the product, should be validated. A risk assessment approach should be used to determine the scope and extent of validation. 本附件描述了确认和验证的原则,应用于药品生产。GMP要求生产者应识别需要进行哪些验证工作,以证明其特定操作中对关键方面的控制。对设施、设备和工艺的重大变更,如果对产品质量产生影响,应进行验证。可以采用评估的方法决定验证的范围和深度。
PLANNING FOR VALIDATION 验证计划
2. All validation activities should be planned. The key elements of a validation programme should be clearly defined and documented in a validation master plan (VMP) or equivalent documents. 所有验证活动均应有计划。一个验证项目的关键要素应进行清楚界定,并在验证主计划(VMP)或相关文件中记录。
3. The VMP should be a summary document which is brief, concise and clear. 验证主计划是一个概述性文件,应简明扼要。
4. The VMP should contain data on at least the following: 验证主计划应最少包括以下内容 (a) validation policy; 验证方针
(b) organisational structure of validation activities; 验证活动的组织结构
(c) summary of facilities, systems, equipment and processes to be validated; 将验证的设施、系统、设备和工艺的概述
(d) documentation format: the format to be used for protocols and reports; 方案和报告的文件格式
(e) planning and scheduling; 计划和时间表
(f) change control; 变更控制
(g) reference to existing documents. 参考文献
5. In case of large projects, it may be necessary to create separate validation master plans. 如果是一个大项目,可能需要创建一个单独的验证主计划
DOCUMENTATION 文件
6. A written protocol should be established that specifies how qualification and validation will be conducted. The protocol should be reviewed and approved. The protocol should specify critical steps and acceptance criteria. 应有书面的验证方案说明如果实施确认和验证。方案应经过审核和批准,应说明关键步骤和可接受标准。
7. A report that cross-references the qualification and/or validation protocol should be prepared, summarising the results obtained, commenting on any deviations observed, and drawing the necessary conclusions, including recommending changes necessary to correct deficiencies. Any changes to the plan as defined in the protocol should be documented with appropriate
justification. 应起草一份与确认和/或验证方案交叉索引的报告,总结所得到的结果,对所有偏差进行评价,作出结论,包括必要时建议的变更以纠正缺陷。对方案中计划的任何变更均应记录并作出适当的评价。
8. After completion of a satisfactory qualification, a formal release for the next step in
qualification and validation should be made as a written authorisation. 在一个令人满意的确认完成后,应有一个正式的书面批准,确认和验证方可进行下一步骤。
QUALIFICATION 确认
Design qualification 设计确认
9. The first element of the validation of new facilities, systems or equipment could be design qualification (DQ). 新的设施、系统或设备验证的首个要素是设计确认(DQ)。
10. The compliance of the design with GMP should be demonstrated and documented. 应论证设计符合GMP要求并记录。
Installation qualification 安装确认
11. Installation qualification (IQ) should be performed on new or modified facilities, systems and equipment. 新的或经过改造的设施、系统和设备应进行安装确认(IQ)。
12. IQ should include, but not be limited to the following: 安装确认应包括,但不仅限于以下内容
(a) installation of equipment, piping, services and instrumentation checked to current engineering drawings and specifications; 应将设备、管道、支持系统和建设的安装情况按照现行的工程图纸和要求进行检查;
(b) collection and collation of supplier operating and working instructions and maintenance requirements; 收集和核对供应商的操作和工作指令和维护要求
(c) calibration requirements; 校正要求
(d) verification of materials of construction. 建筑材料的确认
Operational qualification 运行确认
13. Operational qualification (OQ) should follow Installation qualificatio …… 此处隐藏:18465字,全部文档内容请下载后查看。喜欢就下载吧 ……
相关推荐:
- [外语考试]管理学 第13章 沟通
- [外语考试]07、中高端客户销售流程--分类、筛选讲
- [外语考试]2015-2020年中国高筋饺子粉市场发展现
- [外语考试]“十三五”重点项目-汽车燃油表生产建
- [外语考试]雅培奶粉培乐系列适用年龄及特点
- [外语考试]九三学社入社申请人调查问卷
- [外语考试]等级薪酬体系职等职级表
- [外语考试]货物买卖合同纠纷起诉状(范本一)
- [外语考试]青海省实施消防法办法
- [外语考试]公交车语音自动报站系统的设计第3稿11
- [外语考试]logistic回归模型在ROC分析中的应用
- [外语考试]2017-2021年中国隔膜泵行业发展研究与
- [外语考试]神经内科下半年专科考试及答案
- [外语考试]园林景观设计规范标准
- [外语考试]2018八年级语文下册第一单元4合欢树习
- [外语考试]分布式发电及微网运行控制技术应用
- [外语考试]三人行历史学笔记:中世纪人文主义思想
- [外语考试]2010届高考复习5年高考3年联考精品历史
- [外语考试]挖掘机驾驶员安全生产责任书
- [外语考试]某211高校MBA硕士毕业论文开题报告(范
- 用三层交换机实现大中型企业VLAN方案
- 斯格配套系种猪饲养管理
- 涂层测厚仪厂家直销
- 研究生学校排行榜
- 鄱阳湖湿地景观格局变化及其驱动力分析
- 医学基础知识试题库
- 2010山西省高考历年语文试卷精选考试技
- 脉冲宽度法测量电容
- 谈高职院校ESP教师的角色调整问题
- 低压配电网电力线载波通信相关技术研究
- 余额宝和城市商业银行的转型研究
- 篮球行进间运球教案
- 气候突变的定义和检测方法
- 财经大学基坑开挖应急预案
- 高大支模架培训演示
- 一种改进的稳健自适应波束形成算法
- 2-3-鼎视通核心人员薪酬股权激励管理手
- 我国电阻焊设备和工艺的应用现状与发展
- MTK手机基本功能覆盖测试案例
- 七年级地理教学课件上册第四章第一节




