城市污水处理厂课程设计
3
2万m/d城市污水处理厂工艺方案设计
(学年论文)
课题名称:2万m/d城市污水处理厂工艺方案设计 学生学号:XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX 专业班级:环境监测与治理技术02班
学生姓名:XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX 学生成绩:XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX 指导教师:XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX 课题工作时间:2010-12-27 至 2011-1-7
3
前 言
随着经济飞速发展,人民生活水平的提高,对生态环境的要求日益提高,要求越来越多的污水处理后达标排放。在全国乃至世界范围内,正在兴建及待建的污水厂也日益增多。有学者曾根据日处理污水量将污水处理厂分为大、中、小三种规模:日处理量大于10万m3为大型处理厂,1-10m3万为中型污水处理厂,小于1万m3的为小型污水处理厂。近年来,大型污水处理厂建设数量相对减少,而中小型污水厂则越来越多。如何搞好中、小型污水处理厂,特别是小型污水厂,是近几年许多专家和工程技术人员比较关注的问题。
目 录
第一章 城市污水处理概述--------------------------------------------------------------5 第二章 设计原则、范围与依据---------------------------------------------------------5
2.1 设计原则-------------------------------------------------------------- 2.2 设计范围---------------------------------------------------------------- 2.3 设计依据-------------------------------------------------------------------- 第三章 工艺流程设计-----------------------------------------------------------------5
3.1 污水处理工艺方案比较-------------------------------------------------5
3.2 主要污水处理构筑物选型及设计参数------------------------------------12 3.3 污水处理辅助构筑物设计-----------------------------------------------------14 3.4 污水处理厂平面布置设计------------------------------------------------------15 3.5 污水处理厂高程布置设计-------------------------------------------------------15 3.6 设计计算------------------------------------------------------------16
第四章 经济预算------------------------------------------------------------------------17 第五章 总结------------------------------------------------------------------------------19 致谢----------------------------------------------------------------------------------------------19 参考文献------------------------------------------------------------------------------------------20
1
课程设计(学年论文)摘要(中文):
本次课程设计的题目是2万m3/d城市污水处理厂工艺方案设计。
某城市位于湖北地区,该地区夏季主导风向为东南风,该污水处理工程污水排放量标准为180L/(人·日),总变化系数Kh=1.43,所处理的污水主要污染物有 COD、BOD、SS 和 NH-N等物质,其污水水质如下:BOD5 =230mg/L ,城市污水水质:SS=200mg/L,要求沉淀池的去除率为60%;BOD5=220mg/L,CODCr=480mg/L;当地最高水温为30℃。拟建一座城市污水处理厂,污水厂地形平坦,地基良好,设计标高为47.00米,地下水为标高为41.00米。城市污水总管从污水厂南面进入,干管终点水面标高为42.00米。污水厂北面300米处有一条河流,最高洪水位为45.00米,常水位为41.00米,是该污水处理厂出水的接纳水体。近期(2015年)设计人口为11万人,远期(2025年)设计人口为22万人, 要求经过处理后水质达到《城镇污水处理厂污染物排放标准》(GB18918—2002) 中一级 B标准(BOD5≤20mg/L ,CODCr≤60mg/L,SS≤20mg/L ,TN≤20mg/L, TP≤1mg/L)。 本设计采用厌氧池+DE型氧化沟主体工艺,工艺流程简单,省去了初沉池和污泥消化系统,节省了基建投资和运行费用,同时曝气设备和构造形式多样,运行灵活,管理方便,保证出水达到污水排放标准,做到了水资源的合理利用。
本设计进行了详细的技术方案论证,对工艺处理构筑物进行了选型参数选择和设计计算,对设备进行了选型,进行了平面布置、高程布置、单体构筑物的设计、环境卫生、技术经济分析等方面的设计,污水经处理后可达到要求的排放标准。该污水处理厂总面积为
49150 立方米,总投资为 2642.5 万元,运行费用 为288.35 万元。
2
课程设计(学年论文)摘要(英文):
According to the engineering design, the design of teacher issued task of hubei province city sewage treatment design calculation. The comprehensive consideration, this design main processing structures using oxidation ditch, processed sewage requirements to the town to wastewater treatment plant of standards for pollutants discharge GB18918-2002 level B standard
Through the municipal sewage pipe collection in through the thick grille remove impurities by large suspended after sewage pumping station ascent to wastewater treatment plant. After fine grille enters shaft sinking sand pool streaming sewage into larger inorganic particle removal. Then entered three groove type oxidation ditch, use of sewage sludge are nitrogen phosphorus, reduce the BOD, COD sewage. After the treatment of sewage into contact pool disinfection, meets emission standard. To oxidation ditch produced inside sludge concentration, first in a pool in the belt type filter press pressure filtration dehydration after sinotrans landfill. Design of the whole process of every subject structures such as grille, perpendicular streaming sinking sand pool, 3 oxidation ditch, answer the ditch type touch pool in detail, the system of design calculation and instructions. Theoretically this process is given to BOD, COD, except rate and nitrogen phosphorus removal efficiency. In entailed of enrichment pool, dehydrator design calculation and instructions. Combined with the local terrain elecrtromachinery and design criterion of sewage treatment plants, on layout and elevation calculation thus system determines various processing structures elevation and decorate.
After the treatment of sewage, drainage standard to structures of agriculture an irrigation ditch and relieve hubei elecrtromachinery and improve the water crisis set elecrtromachinery of environmental problems.
3
关键字:城市污水 氧化沟 生物处理 脱氮除磷
Key word: urban wastewater oxidation ditch biological treatm …… 此处隐藏:3776字,全部文档内容请下载后查看。喜欢就下载吧 ……
相关推荐:
- [资格考试]机械振动与噪声学部分答案
- [资格考试]空调工程课后思考题部分整合版
- [资格考试]电信登高模拟试题
- [资格考试]2018年上海市徐汇区中考物理二模试卷(
- [资格考试]坐标转换及方里网的相关问题(椭球体、
- [资格考试]语文教研组活动记录表
- [资格考试]广东省2006年高应变考试试题
- [资格考试]LTE学习总结—后台操作-数据配置步骤很
- [资格考试]北京市医疗美容主诊医师和外籍整形外科
- [资格考试]中学生广播稿400字3篇
- [资格考试]CL800双模站点CDMA主分集RSSI差异过大
- [资格考试]泵与泵站考试复习题
- [资格考试]4个万能和弦搞定尤克里里即兴弹唱(入
- [资格考试]咽喉与经络的关系
- [资格考试]《云南省国家通用语言文字条例》学习心
- [资格考试]标准化第三范式
- [资格考试]GB-50016-2014-建筑设计防火规范2018修
- [资格考试]五年级上册品社复习资料(第二单元)
- [资格考试]2.对XX公司领导班子和班子成员意见建议
- [资格考试]关于市区违法建设情况的调研报告
- 二0一五年下半年经营管理目标考核方案
- 2014年春八年级英语下第三次月考
- 北师大版语文二年级上册第十五单元《松
- 2016国网江苏省电力公司招聘高校毕业生
- 多渠道促家长督导家长共育和谐 - 图文
- 2018 - 2019学年高中数学第2章圆锥曲线
- 竞争比合作更重要( - 辩论准备稿)课
- “案例积淀式”校本研训的实践与探索
- 新闻必须客观vs新闻不必客观一辩稿
- 福师大作业 比较视野下的外国文学
- 新编大学英语第二册1-7单元课文翻译及
- 年产13万吨天然气蛋白项目可行性研究报
- 河南省洛阳市2018届高三第二次统一考试
- 地下车库建筑设计探讨
- 南京大学应用学科教授研究方向汇编
- 2018年八年级物理全册 第6章 第4节 来
- 毕业论文-浅析余华小说的悲悯性 - 以《
- 2019年整理乡镇城乡环境综合治理工作总
- 广西民族大学留学生招生简章越南语版本
- 故宫旧称紫禁城简介