Project Budget Monitor and Control
Author:Yin Guo-li
Nationality:American
Derivation: Management Science and Engineering. Montreal: Mar 20, 2010 .
With the marketing competitiveness growing, it is more and more critical in budget control of each project. This paper discusses that in the construction phase, how can a project manager be successful in budget control. There are many methods discussed in this paper, it reveals that to be successful, the project manager must concern all this methods.
1. INTRODUCTION
The survey shows that most projects encounter cost over-runs (Williams Ackermann, Eden, 2002,pl92). According to Wright (1997)'s research, a good rule of thumb is to add a minimum of 50% to the first estimate of the budget (Gardiner and Stewart, 1998, p251). It indicates that project is very complex and full of challenge. Many unexpected issues will lead the project cost over-runs. Therefore, many technologies and methods are developed for successful monitoring and control to lead the project to success. In this article, we will discuss in the construction phase, how can a project manager to be successful budget control.
2. THE CONCEPT AND THE PURPOSE OF PROJECT CONTROL AND MONITOR
毕业论文
Erel and Raz (2000) state that the project control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliver the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it. The purpose of monitor and control is to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target。
3. SETTING UP AN EFFICIENT CONTROL SYSTEM
For the purpose of achieving cost target, the manager need to set up an efficient management framework including: reporting structure, assessing progress, and communication system. The employees' responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).
4. COST MONITOR AND CONTROL
4.1 Ranking the priority of monitoring
In construction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determined by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Secondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are committed elsewhere. Thirdly, monitoring the activities with less than a
毕业论文
specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).
4.2Methods of cost control
The main cost of a project includes staff cost, material cost and delay cost. To control these cost, managers should first set up a cost control system to: a) Allocate responsibilities for administration and analysis of financial data b) Ensure all costs are properly allocated against project codes
c) Ensure all costs are genuinely in pursuit of project activities
d) Check that other projects are not using the budget.
Then, managers should monitor and control change to the project budget. It means the following things:
a) Concerned with key factors that cause changes to the budget
b) Controlling actual cost changes as they occur
- Monitor cost performance to detect variances
- Record all appropriate changes accurately in the cost baseline
- Preventing incorrect, unauthorized changes being included in the cost baseline
- Determine positive and negative variances
- Integrated with all other control processes (scope, change, schedule, quality)
As a project is dynamic, sometimes the project managers know the project is going out off target by monitoring, but don't know the best action to take. In this circumstance, net present value (NPV) should be used as an ongoing monitor and control mechanism, because NPV takes account of the time element and discounts future cash flows, it is the result of the time effect on cash
4.3 Change monitor and control
Voropajev (1998) states that dynamic changes of project environment will influence the process of project implementation, the project itself and may cause heigh …… 此处隐藏:20903字,全部文档内容请下载后查看。喜欢就下载吧 ……
相关推荐:
- [公文资料]市场营销专员岗位职责
- [公文资料]综合部经理岗位职责
- [公文资料]会计助理岗位职责
- [公文资料]林业站站长职责
- [公文资料]菜品研发部岗位职责
- [公文资料]街道综治办工作职责
- [公文资料]酒店前台的工作职责
- [公文资料]销售部经理岗位职责
- [公文资料]工程部副经理岗位职责
- [公文资料]手术室护士工作职责
- [公文资料]银行客户经理职责
- [公文资料]汽车4s店市场专员职责
- [公文资料]服装店长工作职责
- [公文资料]采购总监岗位职责
- [公文资料]大学行政秘书工作职责
- [公文资料]学校财务人员岗位职责
- [公文资料]财务统计员岗位职责
- [公文资料]物业工程主管工作职责
- [公文资料]公司后勤工作职责
- [公文资料]采矿工程师岗位职责
- 门面出租合同样板(门面出租的合同)
- 自用房屋租赁合同 自住房租房合同(汇总
- 最新酒店劳动合同管理制度(11篇)(酒店
- 2025年无产权车库买卖合同实用(14篇)(
- 建筑工程农民工劳动合同十五篇(通用)(
- 最新深圳标准劳动合同 深圳劳动合同如
- 解除劳动合同通知书(实用6篇)(解除劳动
- 2025年二手房屋买卖合同范围精选(二十
- 最新融资贷款居间合同大全(22篇)(融资
- 2025年个人二手房屋买卖合同协议书四篇
- 2025年果树苗木买卖合约书 签订果树苗
- 广东省劳动合同书填写(21篇)(广东省劳
- 最新餐饮行业没有劳动合同 劳动法餐饮
- 农村土地买卖合同(汇总21篇)(农村土地
- 最新房屋转租合同模版21篇(通用)(标准
- 2025年进口合同号查询五篇(大全)(进口
- 农村建房包工包料合同(通用8篇)(农村建
- 2025年安装监控合同协议书(15篇)(2025
- 2025年企业租赁经营合同(模板9篇)(2025
- 最新郊区土地租赁合同(优质23篇)(最新